Erection of a Dwelling, The Crescent, Bromley Cross, Bolton, BL7
THE PROJECT
Site context.
Practical findings.
The first stage of discharging the condition was to prepare a Phase I desk study report in order to determine if the site has the potential to be impacted by elevated levels of contamination, and to determine the source as well as the likelihood of the risk occurring.
A desk study determines what issues relating to historical contamination may affect the site, this is undertaken by reviewing the site history using a combination of O.S. maps, aerial, plates and street level imagery, a review of data held by regulatory bodies (Environment Agency, local authority, BGS etc.) as well as a site walkover survey.
The history of the site and surrounds were researched using a combination of Ordnance Survey (O.S.) maps, street level imagery and aerial plates, this revealed the site was undeveloped until circa 1955 when the current dwelling was erected. A set of residential garages were noted on the same map 15m south east of the site. Aerial plates indicated the garages were redeveloped prior to 2012.
Street level imagery indicated the site formed part of the gardens of the adjoining dwelling.
The planning history of the site was reviewed as part of the desk based research, no previous applications were noted.
Data provided by regulatory bodies identified a couple of ponds, refuse heap and ground workings within 250m of the site as well as a mill being previously present on the site.
The sensitivity of the groundwater under the site was assessed in order to determine if the site posed a potential risk to groundwater, as there were no abstractions and the site was not near a Source Protection Zone the sensitivity was regarded as very low for both groundwater and surface water bodies.
Once the walkover survey was completed a qualitative risk assessment was undertaken on the potential sources of contamination identified in the desk study report in order to determine if any warranted further investigation, this concluded that there were no credible sources and no further works were warranted.
The report was submitted to discharge the contaminated land planning condition (2776/21), the recommendations within the desk study report were accepted and the condition discharged.
This case study records the project circumstances and conclusions at the time of the work. Planning links may refer to historical council systems.